S.L. 601.03 · Part IV · Types of Procurement Procedures
Regulation 122. Accelerated process
Restricted Procedure
Where a state of urgency duly substantiated by the contracting authorities renders impracticable the time limits laid down in the previous regulation, they may fix:
(a) a time limit for the receipt of requests to participate which shall not be less than fifteen days from the date on which the contract notice was sent;
(b) a time limit for the receipt of tenders which shall not be less than ten days from the date on which the invitation to tender was sent.
Previous regulation
121 — Receipt of tenders
Next regulation
123 — Competitive procedure with negotiation