FAQ
Time limits for tenders
The minimum time limits for the receipt of tenders in an open procedure, when they may be shortened and when they must be extended.
The time limits take account of the complexity of the contract and of the time needed to draw up tenders, without prejudice to the minimum time limits of each procedure (regulation 52(1)). The answers below are for the open procedure (regulation 116).
What is the minimum time limit in an open procedure?
Thirty-five days from the date of publication, for a call for competition that falls under regulation 9(1)(b) (regulation 116(1)(a)). Where the estimated value meets or exceeds the value in Schedule 5, the call is made by a contract notice and the thirty-five days run from the date the notice was sent to the Publications Office of the European Union (regulation 116(1)(b)).
Legal basisregulation 116(1)(a) · regulation 116(1)(b) · official text
And for a contract below the threshold?
Twenty days from the date on which the tender was published, where the estimated value is less than the threshold of regulation 9(1)(a); the time limit may be reduced to fifteen days in cases of extreme urgency (regulation 116(5)).
Legal basisregulation 116(5) · official text
When can the thirty-five days be shortened?
To fifteen days where a prior information notice was published and the conditions of regulation 116(2) are met; to not less than fifteen days where a duly substantiated state of urgency makes the time limit impracticable (regulation 116(3)); and by five days where tenders may be submitted by electronic means (regulation 116(4)).
Legal basisregulation 116(2) · regulation 116(3) · regulation 116(4) · official text
When must the time limit be extended?
Where additional information requested in good time is not supplied at the latest six days before the time limit (four days in an accelerated procedure), and where significant changes are made to the procurement documents (regulation 52(3)). The extension is proportionate to the importance of the information or change (regulation 52(4)).
Legal basisregulation 52(3) · regulation 52(4) · official text
What happens to a tender submitted late?
It is disqualified from the process (regulation 52(6)).
Legal basisregulation 52(6) · official text